When to Start Your School Signage Project (So It Actually Gets Funded)

Written by FASTSIGNS Grand Rapids | Oct 20, 2025 10:00:00 AM

When to Start Your School Signage Project (So It Actually Gets Funded)

This is how signage projects die - not because they're unnecessary, but because they never sync up with your budget timeline.

You've got three weeks until budget submissions are due. Your facilities manager has been asking about new parking lot signage since October. The athletic director wants updated wayfinding for the new gym addition. And you haven't looped in vendors yet because signage keeps getting bumped by more urgent needs.

So they'll probably wait. Again.

By the time you get quotes, the capital budget is locked. When you finally have approval, the fiscal year is ending and the money disappears.

The problem isn't the signage. It's the timing.

When to Bring in a Signage Partner


The difference between a signage project that happens and one that doesn't? Bringing in the right partner at the right time.

Fall (September - November): The Early Bird Window

Best for: Major capital projects for the following fiscal year

This is when next year's capital budget is just starting to take shape. Principals and department heads are submitting requests, and the business office is building the preliminary list.

What to do: If you're planning a significant project - campus rebrand, new building signage, major wayfinding overhaul - connect with your signage vendor now. Get a preliminary quote and scope. This gives you real numbers to include in your capital request instead of guessing.

Why it works: Budget committees are more likely to approve projects that are well-defined with firm pricing. A vague "we need new signs - maybe $30K?" gets cut. A detailed proposal with renderings and a locked quote gets funded.

Winter (December - February): The Critical Planning Phase

Best for: Operating budget projects for the upcoming fiscal year (July start)

Your business office is deep in budget development mode. Department budgets are being finalized. This is your window for getting signage projects into the operating budget.

What to do:

  • Review your campus with fresh eyes (or better yet, have your vendor do a site audit)
  • Identify compliance issues, worn signage, or improvements that would make a real difference
  • Get quotes for projects that could reasonably launch in summer or fall
  • Make the case: "For $15K in the facilities budget, we can solve the visitor wayfinding problem AND update our ADA compliance in the main building"

Why it works: You're catching the budget before it's finalized but after the chaos of fall requests has settled. There's still room to add line items that make sense.

Spring (March - May): The Last Call

Best for: Getting on the radar for next year's planning

By spring, next year's budget is largely set. But this is when you should be documenting issues and building the case for the following year.

What to do:

  • Take photos of problem areas
  • Track complaints and confusion points
  • Start conversations with vendors about long-term solutions
  • Get preliminary concepts and budgets ready for fall budget discussions

Why it works: When budget season rolls around again in the fall, you're not starting from scratch. You've got documentation, you've got vendor relationships, and you've got a head start.

Summer (June - August): The Execution Window

Best for: Actually implementing approved projects

If your project made it into the budget, summer is go-time. School is out (or winding down), which means:

  • Less disruption to students and staff
  • Easier access to buildings for installation
  • Everything ready for the first day of school

What to do: Execute like crazy. Have your vendor lined up, contracts signed, and production scheduled so installation happens in July/August.

Why it works: A fresh campus with new signage on day one of school is worth its weight in gold for staff morale, student orientation, and community perception.

Quick-Turn Options: When You Need Signage Mid-Year

But what happens when you can't wait for the next budget cycle? Maybe there's a new safety requirement, an unexpected facility change, or worn signage that's becoming a problem.

This is where understanding your options becomes critical.

When Mid-Year Requests Make Sense

Sometimes signage needs pop up outside the normal planning cycle:

  • Safety signage required by new regulations or inspections
  • Temporary wayfinding for unexpected building closures or reconfigurations
  • Worn or damaged signs that need immediate replacement
  • Quick campus updates for accreditation visits or major community events

The Budget Workaround: Most districts have mechanisms for mid-year expenditures:

  • Facilities maintenance budgets often have contingency line items
  • Safety and compliance spending can sometimes bypass normal approval processes
  • Bond funds might have flexible allocations for building improvements
  • Some vendors can break projects into phases to fit available budget pockets

What "Education-Ready" Vendors Bring to the Table

When you're working outside the normal budget cycle, you need a vendor who understands school constraints:

They know the approval process: They've worked with school boards before. They know what documentation you need. They can provide quotes in formats that satisfy your business office.

They can work in phases: Can't afford the full project right now? A smart vendor can prioritize the most critical pieces first and schedule the rest for next quarter or next fiscal year.

They have school-friendly timelines: They understand that installation needs to happen during breaks, after hours, or summer. They plan around your calendar, not theirs.

They speak your language: They know what a millage is. They understand capital vs. operating. They've navigated co-op purchasing agreements. You're not explaining your world to them - they already live in it.

Getting Started: Align Your Next Project With Your Budget Reality

The key to successful signage projects isn't just finding the right vendor or getting the best price. It's about understanding your budget cycle and planning accordingly.


If you're in fall or winter right now:
You're in the perfect window to get a signage project into next year's budget. Reach out for a site consultation and preliminary quote. Having real numbers makes your budget request stronger.

If you're in spring or summer: Start documenting what you need for next year's budget cycle. Take photos, note problem areas, and get preliminary conversations started so you're ready when planning begins in the fall.

If you're dealing with a mid-year need: Let's talk about phasing and creative budget solutions. We've helped dozens of Michigan schools navigate mid-year signage needs without breaking the budget.

The team at FASTSIGNS of Grand Rapids has spent years learning the rhythms of school budgets and the real-world challenges you face. We're not just a signage vendor - we're your strategic partner in making campus improvements actually happen.

Ready to get your signage project on the right timeline?

Contact us for a consultation. We'll help you figure out which budget your project belongs in, when to start the conversation with your board, and how to plan a signage project that actually gets funded and installed.

Because the best signage project isn't the biggest one or the flashiest one. It's the one that actually fits your budget cycle and gets done.